AI runs on copper and steel: data centres as a new market for manufacturers in India and Singapore
When people talk about AI, they talk about chips and models. When the people who build data centres talk about AI, they talk about switchgear lead times, busbar trunking, cable trays and chilled water pipes.
In January 2026, STT Global Data Centres India placed purchase orders with a panel maker founded in 1990, with factories in Navi Mumbai and Pune. The job: supply, install, test and commission power distribution panels for one of its data centre projects. By July the orders, with amendments, were worth ₹30.13 crore. The company had been building low and medium voltage panels for factories, metros and solar parks for decades. The skills were the same. The buyer was new.
This guide is for owners and sales leads of manufacturing and engineering companies in India and Singapore: panel builders, cable and wiring makers, sheet metal and structural fabricators, cooling and piping specialists, and the engineering firms around them. It answers one question: can my company sell into the data centre boom, and how? We say where the data is solid, where the numbers disagree and where the conclusion is ours.
At the end you will find a tool, the supply chain map, to work out where your company fits and what buyers will ask you to prove.
Why does AI need so much physical infrastructure?
Because AI runs on electricity, and electricity has to be delivered, converted, distributed and cooled. The International Energy Agency expects global data centre electricity demand to more than double by 2030, to around 945 terawatt-hours, slightly more than Japan uses today. Demand from data centres built for AI is set to more than quadruple (IEA, Energy and AI, April 2025).
Every megawatt of IT load needs a chain of physical kit before a single server switches on: transformers and medium voltage switchgear at the substation, low voltage panels and power distribution units in the halls, backup generators, cables and trays, racks and containment, and cooling plant with its pumps, pipes and manifolds. Most of it is steel, copper and aluminium, assembled and tested by people.
How big is the wave in India, really?
Big, and the numbers vary depending on who counts and what they count.
| India data centre capacity | Figure | Source |
|---|---|---|
| Installed capacity, June 2026 | 1.6 GW | JLL, September 2026 |
| Forecast, 2029 | about 6 GW | JLL, September 2026 |
| Capital needed to get there | about US$110 billion | JLL, September 2026 |
| of which electrical, mechanical and plumbing systems | about US$18 billion | JLL, September 2026 |
| of which IT equipment | about US$88 billion | JLL, September 2026 |
| New capacity absorbed, first half of 2026 | 101 MW, vacancy at a record low of 2.8% | JLL, September 2026 |
Other firms put today's installed base closer to 1.9 GW and their 2030 forecasts anywhere from about 6 GW to 12 GW. Some figures count IT load, some count total power, some count projects that are only planned. Our reading: the direction is not in doubt, the size of the 2030 number is. Plan on the conservative figure and treat anything above it as upside.
Where it is being built. Mumbai and Chennai are the established hubs. JLL expects Hyderabad and Visakhapatnam to become gigawatt-scale markets, helped by announcements such as Google's planned campus in Visakhapatnam and Microsoft's new Hyderabad cloud region.
Why now. The Union Budget 2026-27 offers a tax holiday until 31 March 2047 to foreign cloud providers that serve customers worldwide from data centres in India. JLL reports that the measure has drawn over US$50 billion in foreign capital commitments.
What it means for a supplier. The US$18 billion for electrical, mechanical and plumbing systems is the part a manufacturing SME can realistically compete for. It is spread across thousands of panels, cable runs, racks, pipes and structures, bought through contractors in several cities over several years.
What is happening in Singapore?
Singapore is not building fast. It is building carefully, and that shapes what suppliers can sell.
A rationed market. Singapore had over 1.4 GW of data centre capacity across more than 70 data centres when IMDA published its Green Data Centre Roadmap in May 2024. The roadmap promised at least 300 MW more in the near term, released through competitive calls.
The 2026 round. On 21 August 2026, EDB and IMDA provisionally allocated 200 MW to four operators, 50 MW each: Digital Realty, Equinix, Keppel Data Centres and ST Telemedia Global Data Centres. All four will build on Jurong Island, where JTC is developing a low-carbon data centre park. All four must power more than half their capacity from green energy, reach Green Mark for Data Centres Platinum and use liquid cooling (EDB and IMDA, August 2026). The agencies will review the need for another round in 18 to 24 months.
The liquid cooling standard. On 27 August 2026, Singapore published SS 726:2026, Liquid Cooling in Tropical Data Centres, described as the world's first standard of its kind. It addresses the problems heat and humidity create for liquid cooling, such as corrosion, and recommends ways to measure and reduce water use (IMDA and Enterprise Singapore, August 2026).
Our reading: in Singapore, the volume is modest but the specification is demanding and new. A precision engineering or piping firm that learns SS 726 early, and can show it, has something few competitors can claim. That expertise also travels to data centre projects in neighbouring markets, which are often managed from Singapore offices.
A regional example. In January 2026, Oxford Innotech, an engineering firm listed in Malaysia, won a RM4.8 million contract to supply precision steel components for a data centre airflow management system. The customer was the Singapore office of an Australian data centre infrastructure specialist, and the end user a US technology group (The Star, January 2026). It is a small contract, and a clear picture of how the chain works: the SME sold to a specialist, not to the hyperscaler.
What's inside a data centre, and which parts can an SME make?
| Component | What it does | Who usually makes it | Room for SMEs |
|---|---|---|---|
| Power transformers and medium voltage switchgear | Bring grid power in and step it down | Large OEMs | Low, except as subcontracted fabrication, enclosures and testing |
| Low voltage panels, PCC and MCC panels, PDUs | Distribute power to halls and racks | Panel builders, often using ABB, Siemens or Schneider parts | High |
| Busbar trunking, cables, cable trays and ladders | Carry power and data | Cable makers, fabricators | High |
| Diesel generator synchronising panels and fuel systems | Backup power | Panel builders, mechanical contractors | Medium to high |
| Racks, cabinets, aisle containment, airflow panels | Hold servers and steer air | Sheet metal and enclosure makers | High |
| Chillers and cooling distribution units | Remove heat | Large OEMs | Low |
| Liquid cooling pipework, manifolds, skids and supports | Carry coolant to the chips | Piping, welding and precision engineering firms | Medium to high, growing |
| Steel structures, platforms, pipe racks, louvres | Hold the building's services | Structural fabricators | High |
Our reading: the high-room rows have one thing in common. Buyers need many of them, built to drawings and delivered on site in sequence. That rewards suppliers who can scale, document and deliver on time more than those with a unique technology.
Where are the bottlenecks, and why do they help you?
Lead times. In a Wood Mackenzie survey from the second quarter of 2025, switchgear took an average of 44 weeks to deliver and power transformers 128 weeks. Prices for power transformers rose 77% since 2019, and for medium voltage switchgear 50% since 2021 (Wood Mackenzie, via POWER magazine, January 2026).
That survey covers the United States. We found no comparable published survey for India or Singapore, so treat the numbers as a signal of global pressure, not a local quote. The pressure is the same in kind: copper, electrical steel and skilled assembly are in demand everywhere at once.
Our reading: when the big names quote long waits, contractors look for capable second sources. A panel builder who can deliver a tested, documented panel in weeks, not months, has a sales argument no brochure can beat.
Who actually buys?
Usually not the name on the building.
- The operator or hyperscaler (STT, Equinix, Digital Realty, Keppel, NTT, Nxtra, AdaniConneX, or a cloud provider building its own) sets the specifications and the approved vendor list.
- The developer or owner's engineer turns those specifications into designs and tender packages.
- The main contractor and the MEP contractor (mechanical, electrical and plumbing) buy most of the kit, schedule deliveries and carry the risk if something arrives late.
- Specialists in power, cooling or containment buy components from smaller firms, as in the Oxford Innotech case.
For most SMEs, the realistic first customer is the MEP contractor or a specialist, with the operator's approval behind it. Some panel makers, like the example above, sell directly to the operator once they have a track record.
What will buyers ask you to prove?
Before you reach a tender, you have to get on the list. Buyers check the same things again and again:
- Product standards. For low voltage panels, IEC 61439 and its Indian adoption, with type-test certificates. For components, the relevant IEC or IS standard and, for some international customers, UL listings.
- Quality and safety systems. ISO 9001 at a minimum, often ISO 45001 for site work and ISO 14001 for environmental management.
- Data centre specifics. In Singapore, familiarity with Green Mark for Data Centres and, for cooling work, SS 726:2026. Operators building to Uptime Institute tiers will expect documentation that fits those designs.
- Capacity and delivery. Factory size, monthly output, current order book and on-time delivery record. Factory acceptance tests that the buyer can witness.
- References. Similar projects, ideally for critical facilities such as hospitals, airports, metros or semiconductor plants, with names you are allowed to share.
- Partnerships. Many panel builders work with switchgear OEMs. Say which ones, and at what level.
None of this is new to a good manufacturer. What is often missing is that none of it is visible. Buyers research suppliers long before they call, as we explained in how manufacturing buyers choose suppliers. If your website does not show your standards, capacity and references, you are not on the shortlist.
The supply chain map: where does your company fit?
The supply chain map takes each data centre component from the table above and asks four questions about your company. Fill it in with your production and sales leads. It takes about an hour.
| Question | Answer for each component |
|---|---|
| 1. Can we make it? | Yes today / With a new certificate or machine / No |
| 2. Can we prove it? | Certificates, type tests and references in hand / Partly / No |
| 3. How fast can we deliver? | Weeks / A few months / Longer than the market leaders |
| 4. Who would buy it from us? | Operator / MEP contractor / Specialist / Not sure |
How to read your map
- Yes, proven, fast: this is your entry product. Build a reference sheet and a page for it, and contact MEP contractors and specialists working on projects in your region.
- Yes, but not proven: this is your next investment. A type test, a certificate or a first small order is usually the missing step.
- Fast delivery where leaders are slow: lead with it. Lead time is the bottleneck buyers feel most.
- Not sure who buys: start by mapping the contractors on current projects. Operators publish their projects; contractors often publish their wins.
What should owners do in the next 12 months?
- Fill in the supply chain map for every component you could make. Pick one or two entry products.
- Close the proof gaps on those products: type tests, certificates, a witnessed factory acceptance test.
- Build a references page with projects in critical facilities, even outside data centres.
- Publish your capacity: factory area, monthly output, lead times, OEM partnerships and standards, written for an engineer who is comparing you with three others.
- List the contractors working on data centre projects in your region and introduce yourself with a one-page capability sheet.
- In Singapore, get your engineers familiar with SS 726:2026 and Green Mark for Data Centres. In India, follow the projects in Mumbai, Chennai, Hyderabad and Visakhapatnam, where most of the new capacity is going.
Where does EGGA fit?
EGGA does not sell switchgear or build data centres. We are a growth, sales and marketing service for SME owners, on one fixed monthly fee. For manufacturers moving into a new market like this one, that means turning what you already do well into proof buyers can find: a website and capability pages that show standards, capacity and references, visibility on Google and AI search for the terms contractors use, and a steady flow of qualified enquiries.
If you want to see where your company stands today, the Growth X-Ray gives you a free, research-based diagnostic. Plans and prices for India and Singapore are on our pricing pages.
The opening goes to the supplier buyers can verify
The data centre boom is often told as a story about chips and cloud contracts. For a manufacturer, it is a story about panels, pipes and delivery dates. India needs billions of dollars of electrical and mechanical systems in the next three years, and Singapore is writing the rules for liquid cooling in the tropics.
The companies that win will not always be the biggest. They will be the ones that can prove what they make, deliver when the big names cannot and are easy to find when a contractor starts looking.
Questions people also ask
How can a small manufacturer become a data centre supplier?
Start with a product you already make and can certify, such as low voltage panels, cable trays, racks or pipework. Get the type tests and quality certificates buyers expect, build references from similar critical projects, and approach MEP contractors and specialists working on data centre projects. Most first orders come through contractors, not operators.
How big is India's data centre market?
JLL puts India's installed data centre capacity at 1.6 GW in June 2026 and expects about 6 GW by 2029, requiring about US$110 billion of investment. Of that, about US$18 billion goes to electrical, mechanical and plumbing systems. Other firms' forecasts for 2030 range from about 6 GW to 12 GW.
How much data centre capacity is Singapore adding?
In August 2026, Singapore provisionally allocated 200 MW to Digital Realty, Equinix, Keppel Data Centres and ST Telemedia Global Data Centres, 50 MW each, all on Jurong Island. Singapore had over 1.4 GW across more than 70 data centres in 2024. Another allocation round will be considered in 18 to 24 months.
What is SS 726:2026?
SS 726:2026 is Singapore's standard for liquid cooling in tropical data centres, published by IMDA and Enterprise Singapore in August 2026. It gives guidance on designing, deploying and operating liquid cooling systems in hot and humid conditions, including corrosion risks, integration with air cooling and water use.
Which standards apply to data centre electrical panels?
Low voltage switchgear and controlgear assemblies are covered by IEC 61439, adopted in India as IS/IEC 61439. Buyers usually also expect ISO 9001 quality certification, type-test reports and witnessed factory acceptance tests. Requirements vary by operator, so ask for the specification early.
Why are lead times for electrical equipment so long?
Demand for transformers and switchgear has grown faster than factory capacity, while copper and electrical steel prices have risen. In a 2025 Wood Mackenzie survey of the US market, switchgear took about 44 weeks and power transformers about 128. Suppliers who can deliver faster have a strong advantage.
Sources
- AI is set to drive surging electricity demand from data centresInternational Energy Agency, on the Energy and AI report, 10 April 2025, 2025
- India's data centre capacity expected to jump to 6 GW by 2029IANS, on a JLL report, 2 September 2026. Secondary source, 2026
- Budget 2026-27: Govt offers tax holiday till 2047 to global cloud firmsAutocar Professional, February 2026. Secondary source, 2026
- Fact sheet: four data centre proposals selected as part of the second Data Centre Call for ApplicationEDB and IMDA, 21 August 2026, 2026
- Singapore launches world's first liquid cooling standard for data centres in tropical climatesEnterprise Singapore and IMDA, 27 August 2026, 2026
- Factsheet: IMDA Green Data Centre RoadmapIMDA, 30 May 2024, 2024
- Transformers in 2026: shortage, scramble, or self-inflicted crisis?Sonal C. Patel, POWER magazine, on Wood Mackenzie data, 2 January 2026, 2026
- Vivid Electromech strengthens data centre footprint with ₹30.13 Cr order from STT Global Data Centres IndiaVivid Electromech, press release filed with NSE, 13 July 2026, 2026
- Oxford Innotech wins RM4.8mil data centre jobThe Star, 21 January 2026, 2026